Question: Consider your calculations from the previous question. If the critical path is A-B-E-F-I , which activity should be crashed first. Given the above table of

Consider your calculations from the previous question.
If the critical path is A-B-E-F-I, which activity should be crashed first.
Given the above table of Software Developing Project, calculate the following: Slope? Maximum crash time? Provide your answers in the table below. Activity Slope Max crash time Normal Normal Crash Time Cost Time Crash Cost A 18 B 16 2 7 9 15 10 12 16 8 C D E $4,000 $5,500 $6,100 $4,700 $2,050 $1,200 $7,200 $7,500 $1,750 4 $ 4,500 $ 7,000 $ 7,900 $ 5,000 $ 2,300 $ 1,700 $ 7,400 $ 8,000 $ 1,750 IF 16 15 G H 9 4 7 2 2Step by Step Solution