Question: A hammock activity is one which: Indicates that the project work pauses and then resumes Terminates one path of the network Summarizes a group of

A "hammock" activity is one which:
Indicates that the project work pauses and then resumes
Terminates one path of the network
Summarizes a group of detailed activities
Has zero duration but which utilizes resources