Question: A house flipper found a diamond in the rough and, after buying it at a sheriff's auction, has identified six systems that need significant work.

A house flipper found a diamond in the rough and, after buying it at a sheriff's auction, has identified six systems that need significant work. The estimated completion times (in weeks) and costs are identified in the table alongside a set of expedited completion times and the crash costs.
\table[[Activity,Normal time,Crash time,Normal Cost,Crash Cost,Predeces],[A,10,7,5,000,7,200,],[B,15,10,10,000,15,000,A],[C,20,15,18,000,24,000,B],[D,20,17,20,000,26,000,],[E,15,12,12,000,14,700,D],[F,12,7,7,200,12,700,E]]
What is the shortest time to complete this project?
a.33 weeks
b.34 weeks
c.35 weeks
d.36 weeks
 A house flipper found a diamond in the rough and, after

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!