Question: a. How many weeks should we crash the first activity? b. What is the total project cost after we crash the first activity? c. Which

a. How many weeks should we crash the first activity?
b. What is the total project cost after we crash the first activity?
c. Which activity we should crash next?
d. How many weeks should we crash the 2nd activity?
e. What is the total project cost after we crash the second activity?
B 3 D F C E 4 Table 7.7 NORMAL TIME 4 AVAILABLE WEEKS OF CRASHING CRASH TIME 2 ACTIVITY A CRASHING COST / WEEK CRASH NORMAL COST COST ($000s) ($000s) 8 14 9 11 10 10 10 15 11 14 B 3 2 4 4 D 3 5 4 E 1 F 1 1 6 6 Indirect project cost = $2000 per week Penalty cost = $5000 per week past week 12Step by Step Solution