Question: Suppose that the normal time for activity H is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks

Suppose that the normal time for activity H is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks with the crash cost of $12,000.

What will be the total activity cost if we crash it to 5 weeks ?

A. $3000

B. $11,000

C. $8,000

D. $13,000