Question: A) if you had an activity with a optimistic time of 4, a most likely estimate of 6, and a pessimistic estimate of 9, what
A) if you had an activity with a optimistic time of 4, a most likely estimate of 6, and a pessimistic estimate of 9, what would the expected time for the activity be? Answer to one decimal place. B) if you had an activity with a optimistic time estimate of 2 , a most likely estimate of 5, and a pessimistic of 8, what would the variance for the activity be? Answer to two decimal places. C) what is the expected completion time for the project?

Add attachments to support your work Project Management - Incorporating Uncertainty An advertising agency CEO has gathered the activity information for a new advertising campaign as shown in the accompanying table. Time estimate weeks Activity Optimistic Most Likely Pessimistic Immediate Predecessors 6 3 6 B - O WOW N - 13 14 A 6 12 A,C 8 16 B 5 6 EF Draw the network and use it to answer the following questions
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts