Question: Question 42 What is the expected time if an activity has a optimistic time of 4 days, a likely time of six days and a

Question 42

What is the expected time if an activity has a optimistic time of 4 days, a likely time of six days and a pessimistic time of 8 days?

Select one:

a. 6 days

b. 4 days

c. 8 days

d. 7 days