Question: A key for developing project cost estimates is to: a. Cost the project while considering the total package b. Cost the project on a major
A key for developing project cost estimates is to:
a. Cost the project while considering the total package
b. Cost the project on a major module basis
c. Cost the project on a work package and task basis
d. Cost the project and add 33% for contingency