Question: A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the

A local project being analysed by PERT has 42 activities, 13 of

A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the critial path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less? | Give your answer to 4 decimal places. I