Question: A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the
A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the critial path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less? | Give your answer to 4 decimal places. I
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
