Question: a local project being analyzed by pert has 42 activities, 15 of which are on the critical path. If the estimated time along the critical
a local project being analyzed by pert has 42 activities, 15 of which are on the critical path. If the estimated time along the critical path is 115 days and the sum of variances along the critical path is 64 days, what is the probability that the project will take at least 125 days to complete?
Some Z values from the table: 0.20= 58.8%, 0.25= 60%, 1.04= 85%, 1.28= 90%, 1.65= 95%, 2.06= 98%