Question: a m PREDECESSORS 4 Q1. Please answer the following on the answer sheet. (30 Marks) ACTIVITY b A 1 5 B 2 2 2 4

a m PREDECESSORS 4 Q1. Please answer the
a m PREDECESSORS 4 Q1. Please answer the following on the answer sheet. (30 Marks) ACTIVITY b A 1 5 B 2 2 2 4 2 3 D 6 3 2 E 5 3 3 F 4 2 4 G 3 2 5 H 2 2 4 1 2 3 6 MNMNMM A A B CD E,F D GH a) Please calculate the network diagram using activity times (Please DO NOT USE HAND DRAWINGS) b) Please calculate ES, LS, EF, LF for each activity c) Please calculate slack for each time activity d) Show the critical path e) Calculate Z-probability for project completion within 34 days. If z>5 so probability is 0.75/75%or if Z