Question: A machine operator uses the first-come first served rule to schedule 10 jobs on a press machine. The total processing time of the 10 jobs

A machine operator uses the first-come first
A machine operator uses the first-come first served rule to schedule 10 jobs on a press machine. The total processing time of the 10 jobs is 55 minutes and the machine run with a 75% utilization. Based on these information, calculate the average completion time