Question: A machine operator uses the first-come first-served rule to schedule 10jobs on a press machine. The total processing time of the 10 jobs is 65

A machine operator uses the first-come first-served rule to schedule 10jobs on a press machine. The total processing time of the 10 jobs is 65 minutes and the machine run with a 36% utilization. Based on these information, calculate the average completion time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!