Question: A major weakness with project completion time analysis with uncertain activity times is the q , possibility that more than one critical path might exist

A major weakness with project completion time analysis with uncertain activity times is the
q,
possibility that more than one critical path might exist
need to solicit three time estimates for each activity
assumption that the project completion time is normally distributed q,
bias associated with the expected project completion time
 A major weakness with project completion time analysis with uncertain activity