Question: A manager is wanting to develop a Gantt Chart for an upcoming project. Which two factors does this manager need to develop the chart? The
A manager is wanting to develop a Gantt Chart for an upcoming project. Which two factors does this manager need to develop the chart?
The quality requirements and the tasks to be completed
The tasis to be completed and estimated completion times
The tasks to be completed and the order in which they will be completed
Just the tasks to he completed
The order in which the tasks will be completed and the quality requirements