Question: A manufacturing firm would like to develop an aggregate plan for the next quarter. Data related to the demand, capacity and cost are shown below.

A manufacturing firm would like to develop an aggregate plan for the next quarter. Data related to the demand, capacity and cost are shown below.

Months

Jan

Feb

March

Demand

800

1000

900

Capacity

Regular

700

700

700

Subcontracting

150

150

150

Overtime

100

100

100

Start inventory

0

Regular time cost = Rs. 1000/unit, Overtime cost=Rs. 1200/unit, Subcontracting cost = Rs. 1500/unit, Inventory carrying cost = Rs. 50/unit per month. Solve this aggregate planning problem to minimize the total cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!