Question: A masonry contractor is preparing an estimate for building a stone wall and gate. He estimates that the job will take a 4 0 -

A masonry contractor is preparing an estimate for building a stone wall and gate. He estimates that the job will take a40-hour work week. He plans to have three laborers at $1313 per hour and six masons at $1818 per hour. He'll need $3125 worth of materials and wishes to make a profit of $400.
Write a mathematical statement that will give the estimated cost of the job. Then, calculate this total.