A Moving to another question will save this response. Question 6 of 32 > >> Question 6 0.33 points Save Answer In a project network, the project completion time has been determined to be a random variable with a mean of 76 days and a standard deviation of 9 days (and can be assumed to be Normally distributed). How many days should we allow for this project to have approximately 90% probability of completion? (Provide one decimal place)