Question: A ( n ) _ _ _ _ _ _ _ _ _ _ _ _ _ calculates how late an activity can start and
An calculates how late an activity can start and finish.
Multiple Choice
forward pass
backward pass
circular pass
complete enumeration
late finish
Multiple Choice
burst
parallel
merge
critical
dangling
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!