Question: A ( n ) _ _ _ _ _ _ _ _ _ _ _ _ _ calculates how late an activity can start and

A(n)_____________ calculates how late an activity can start and finish.
Multiple Choice
forward pass
backward pass
circular pass
complete enumeration
late finish
Multiple Choice
burst
parallel
merge
critical
dangling