Question: Scheduling Exercise 6 Critical Path Method ( CPM ) Activity on the Arrow ( AOA ) Forward Pass, Backward Pass, Total Float Scheduler: _ _
Scheduling Exercise
Critical Path Method CPM
Activity on the Arrow AOA
Forward Pass, Backward Pass, Total Float
Scheduler: Date:
Due by: date and time Points
For each project, verify if the diagram is correct; add or remove requisite links arrows
dummies Do a forward pass to calculate the early start and the early finish of each activity.
Do a backward pass to calculate the late start and the late finish of each activity. Determine the
total float of each activity. Highlight the critical path on the CPM diagram and answer the
following questions point each:
Part Points
How long does the project take? days
What is the early start of activity N day
What is the late finish of activity O day
Which activity lists a redundant predecessor
Part Points
How long does the project take? days
What is the late start of activity R day
What is the early finish of activity L day
If activity D is delayed by days,
what is the length of the overall project? days
If activity T is delayed by days,
what is the length of the overall project? days
What activities are on the critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock