Question: A negative CV or SV value indicates that the project is: Group of answer choices Under cost or behind schedule Over cost or ahead of
A negative CV or SV value indicates that the project is: Group of answer choices Under cost or behind schedule Over cost or ahead of schedule Under cost or ahead of schedule Over cost or behind schedule On cost or on schedule