Question: Based on the baseline plan below (critical tasks are in red/bold font) and the update received at the end of the 4th period, this project
Based on the baseline plan below (critical tasks are in red/bold font) and the update received at the end of the 4th period, this project appears to be:
| Task | Budget | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A | 3000 | 1500 | 1500 | |||||||||
| B | 3000 | 1500 | 1500 | |||||||||
| C | 2000 | 400 | 400 | 400 | 400 | 400 | ||||||
| D | 2500 | 1000 | 500 | 500 | 500 | |||||||
| E | 1600 | 400 | 400 | 400 | 400 | |||||||
| F | 2000 | 500 | 500 | 500 | 500 | |||||||
| Cumulative | 1500 | 3000 | 5900 | 8300 | 9600 | 10900 | 11700 | 12600 | 13100 | 13600 | 14100 | |
Update at the end of 4th Period:
| Task | % Complete | EV | AC | PV | CV | SV |
|---|---|---|---|---|---|---|
| A | 100% | 3000 | 3000 | 3000 | 0 | 0 |
| B | 100% | 3000 | 2800 | 3000 | 200 | 0 |
| C | 50% | 1000 | 2000 | 800 | -1000 | 200 |
| D | 50% | 1250 | 1500 | 1500 | -250 | -250 |
| Cumulative Totals | 8250 | 9300 | 8300 | -1050 | -50 | |
Group of answer choices
Running behind of its schedule
Running ahead of its schedule
Running right on schedule
Not enough information to answer the question