Question: Based on the baseline plan below (critical tasks are in red/bold font) and the update received at the end of the 4th period, this project

Based on the baseline plan below (critical tasks are in red/bold font) and the update received at the end of the 4th period, this project appears to be:

Baseline Plan
Task Budget 1 2 3 4 5 6 7 8 9 10 11
A 3000 1500 1500
B 3000 1500 1500
C 2000 400 400 400 400 400
D 2500 1000 500 500 500
E 1600 400 400 400 400
F 2000 500 500 500 500
Cumulative 1500 3000 5900 8300 9600 10900 11700 12600 13100 13600 14100

Update at the end of 4th Period:

Progress Update
Task % Complete EV AC PV CV SV
A 100% 3000 3000 3000 0 0
B 100% 3000 2800 3000 200 0
C 50% 1000 2000 800 -1000 200
D 50% 1250 1500 1500 -250 -250
Cumulative Totals 8250 9300 8300 -1050 -50

Group of answer choices

Running behind of its schedule

Running ahead of its schedule

Running right on schedule

Not enough information to answer the question

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!