Question: A new copper mine is to be started - up . A 6 0 m wide orebody outcrops on surface and dips at 8 5

A new copper mine is to be started-up. A 60m wide orebody outcrops on surface and dips at
85 degree towards the south. The orebody is economic up to 200m below surface. From
200m further deep the grades are very poor. Open pit has a limit of 150m. below that an
underground mine has to take over. Underground equipment will include LHDs, drill rigs,
some of which are at most 4m wide and 5m high. A representative log of the host rock is
shown.
Given that:
3 joints sets are prevalent this environment. The joints are mostly curved and slickensided, with some fine material infilling.
Joint sets Dip (degrees) Dip direction(degrees) Ave. Joint spacing
J1781101m
J2603000.6m
J370700.3m
RQD =60
The host rock is slightly moist and wet in some locations
K ratio =1.6
Standard safety factor for the mine is 1.3 as a matter of policy ( be it dumps, slopes,
underground support, etc.). A company has requested you to perform a geotechnical design
feasibility .PART B
Given that the cost of waste removal is R30/m3, ore material sells at R1000/ton. Determine
the percentage gain in the open pit as a result of increasing overall slope angle by 1 degreety.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!