Question: A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure. From the information shown, generate: a) An indented bill
A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure. From the information shown, generate: a) An indented bill of material for product A b) Net requirements for each part to produce 13As in week 8 using lot-for-lot. Please explain all in details.

\begin{tabular}{cc} \hline PART & INVENTORY ON HAND \\ \hline A & 0 \\ B & 2 \\ C & 10 \\ D & 5 \\ E & 4 \\ F & 5 \\ G & 1 \\ H & 10 \\ \hline \end{tabular} PART STRUCTURE TREE LT= lead time in weeks (1)= All quantities =1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts