Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. table [ [ Activity , Preceding, table
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
tableActivityPreceding,tableOptimisticTimetableProbableTimetablePessimisticTimetableExpectedTimeVarianceBACADAEBFBGC FHDIHJG I,KE J
a Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above.
b Which activities form the critical path?
c What is the estimated time of the critical path?
d What are the project variance and the project standard deviation?
e What is the probability of completion of the project before week