Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected
- A partially solved PERT problem is detailed in the table below. Times are given in weeks.
| Activity | Preceding | Optimistic Time | Probable Time | Pessimistic Time | Expected Time | Variance |
| A | -- | 7 | 9 | 14 |
| 1.361 |
| B | A | 2 | 2 | 8 |
| 0 |
| C | A | 8 | 12 | 16 |
| 0 |
| D | A | 3 | 5 | 10 |
| 1.361 |
| E | B | 4 | 6 | 8 |
| 0 |
| F | B | 6 | 8 | 10 |
| 0 |
| G | C, F | 2 | 3 | 4 |
| 0 |
| H | D | 2 | 2 | 8 |
| 1.000 |
| I | H | 6 | 8 | 16 |
| 2.778 |
| J | G, I | 4 | 6 | 14 |
| 2.778 |
| K | E, J | 2 | 2 | 5 |
| 0.250 |
Calculate the expected time for each activity.