Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. 1 . Calculate the expected time for each activity.
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. Which activities form the critical path? What is the estimated time of the critical path? What are the project variance and the project standard deviation?tableActivityPreceding,tableOptimisticTimetableProbableTimetablePessimisticTimetableTimeTimectedVarianceABACADAEBFB CGC D FHD GIG HJG I,KE F J
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
