Question: A PERT / CPM activity has an optimistic time estimate of 7 days, a most likely estimate of 8 days, and pessimistic estimate of 1

A PERT/CPM activity has an optimistic time estimate of 7 days, a most likely estimate of 8 days, and pessimistic estimate of 11 days. The standard deviation of the duration of the activity is