Question: A PERT / CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is
7.0
7.5
8.0
8.5
10.0
None of the above
 A PERT/CPM activity has an optimistic time estimate of 3 days,