Question: A PERT / CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time
A PERTCPM activity has an optimistic time estimate of days, a most likely time estimate of days, and a pessimistic time estimate of days. The expected time in days of this activity is
None of the above