Question: A PERT / CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is