Question: A PERT diagram indicates that there are three (3) paths in a project. The first path A-B-E-K has a path length of 22.5 weeks. The

A PERT diagram indicates that there are three (3) paths in a project. The first path A-B-E-K has a path length of 22.5 weeks. The second path A-B-F-G-J-K has a path length of 34.67 weeks. The third path A-C-G-J-K has a path length of 36.83 weeks. Given the information in the table below, what is the closest probability that this project will be completed in 39 weeks?A PERT diagram indicates that there are three (3)

Activity Optimistic Time Most Likely Time Pessimistic Activity Time Std. Dev. 15 1.000 9 1.167 A 9 10 B 2 3 10 14 18 1.333 COLLO E 2 6 8 1.000 F 6 8 10 0.667 2 2 3 4 0.333 G J 3 6 14 1.833 K 1 2 5 0.667

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!