Question: A PERT diagram indicates that there are three (3) paths in a project. The first path A-B-E-K has a path length of 22.5 weeks. The
A PERT diagram indicates that there are three (3) paths in a project. The first path A-B-E-K has a path length of 22.5 weeks. The second path A-B-F-G-J-K has a path length of 34.67 weeks. The third path A-C-G-J-K has a path length of 36.83 weeks. Given the information in the table below, what is the closest probability that this project will be completed in 39 weeks?