Question: A planned order release is The planned order receipt adjusted for lead time. The planned order receipt adjusted for on hand inventory. The gross requirement
A planned order release is
The planned order receipt adjusted for lead time.
The planned order receipt adjusted for on hand inventory.
The gross requirement adjusted for onhand inventory.
The net requirement adjusted for lot size.