Question: A process engineer can produce an item using Machine A or B. Machine A has fixed cost of $3000 for tooling and a variable cost
A process engineer can produce an item using Machine A or B. Machine A has fixed cost of $3000 for tooling and a variable cost of $7 per unit. Machine B requires a special machine with a fixed cost of $22,000 and a variable cost of $3 per piece. How many units should be produced to get less cost in Machine B than A?
Select one:
a. 5000
b. 4500
c. 3500
d. 6000
e. 4750
f. 4000