Question: A process for a project has 3 paths. The project is complete when all the paths are complete. Path 1 takes 39.5 minutes Path 2
A process for a project has 3 paths. The project is complete when all the paths are complete. Path 1 takes 39.5 minutes Path 2 takes 44.6 minutes Path 3 takes 25.2 minutes The flow time of this process in minutes with one significant digit is