Question: A process for a project has 3 paths. The project is complete when all the paths are complete. Path 1 takes 39.5 minutes Path 2

A process for a project has 3 paths. The project is complete when all the paths are complete.

Path 1 takes 39.5 minutes

Path 2 takes 44.6 minutes

Path 3 takes 25.2 minutes

The theoretical flow time for this process is 22 minutes.

What is the flow efficiency of this process? Express your answer as a decimal with three significant digits (not percentage)