Question: A process for a project has 3 paths. The project is complete when all the paths are complete. Path 1 takes 3 9 . 5

A process for a project has 3 paths. The project is complete when all the paths are complete.
Path 1 takes 39.5 minutes
Path 2 takes 44.6 minutes
Path 3 takes 25.2 minutes
critical path