Question: A process has 2 steps. The first step uses a cutting machine that takes 10 minutes to cut one part. However, this cutting machine requires
A process has 2 steps. The first step uses a cutting machine that takes 10 minutes to cut one part. However, this cutting machine requires a setup of 20 minutes before each batch. The second step uses a machine to paint the parts produced in the first step. Painting takes 20 minutes per part.
Assuming that the process has unlimited demand, what is the ideal batch size?
a. 2
b. 10
c. 3
d. 20
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts