Question: A process heat recovery study identifies five potential modifications, none of which are mutually exclusive, with the costs and energy savings given below. Project Capital
A process heat recovery study identifies five potential modifications, none of which are mutually exclusive, with the costs and energy savings given below.
| Project | Capital Cost ($MM) | Fuel Savings (MMBtu/hr) |
| A | 1.6 | 15 |
| B | 0.6 | 9 |
| C | 1.8 | 16 |
| D | 2.2 | 17 |
| E | 0.3 | 8 |
If fuel costs $6/MMBtu and the plant operates for 350 days/year: What is the maximum 10-year NPV that can be achieved with a 15% interest rate and a 35% tax rate? Assume all the projects can be built immediately, and use MACRS depreciation with a five-year recovery term. What combination of projects is selected to meet the minimum NPV?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
