Question: confused A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for
confused
A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for the next week is as follow Dayt: : 20 : 26 Day 2 : 10 : 15 Day 3: : 20 : 19 Day 4: : 18 : 20 Day 5: : 12 : 20 s (Round your answer to 5 decimal place.) ) What is the take time of the process? hours/unit What would a level production schedule look like? ABABABABB ABABABABB ABABABABA ABABABABA O BABABABAB ABABABABA CARABABABA BABABABAB