A process uses four machines called A, B, C, and D to produce their two products called
Question:
A process uses four machines called A, B, C, and D to produce their two products called X and M. Product X sells for $10 and product M sells for $15. The table shows how long each product is processed on each machine. Each machine is available for 8 hours per day and the company has demand for 15 Xs and 20 Ms. Machine Product X Product M A 15 min/unit 15 min/unit B 25 min/unit 5min/unit C 20 min/unit 10 min/unit D 10 min/unit 20 min/unit What is the best product mix for the company?
Machine | Product X | Product M |
A | 15 min/unit | 15 min/unit |
B | 25 min/unit | 5 min/unit |
C | 20 min/unit | 10 min/unit |
D | 10 min/unit | 20 min/unit |
What is the best product mix for the company?