Question: A product manager has the following data about the project. Please answer the following questions according to this data: What is the total project time

A product manager has the following data about the project. Please answer the following questions according to this data: What is the total project time Draw the Gantt diagram Find the critical activities activity precedor activity duration (week) A 8 B A 8 A 12 D 6 E B 2. F E.C 8 G EC 3 H F 2 F 6 j D,G,H 6 K K 1. J