Question: A product structure tree ( BOM ) is shown below. 4 0 0 Scissors are need on Day 5 Lead times - 1 day for

A product structure tree (BOM) is shown
below.
400 Scissors are need on Day 5
Lead times -1 day for each component and
final scissor assembly, and 2 days for the
plastic grips
On hand inventory: Bottom Blade Assembly =
25, Straight Blade =100, and Bent Plastic Grips
=150
Answer the following questions
Determine the planned order release of scissors
how many and when?
Determine the planned order release of the
bottom blade assembly how many and when?
Determine the planned order release of the
straight blade how many and when?
Determine the planned order release of the bent
plastic grips how many and when?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!