Question: A product structure tree ( BOM ) is shown below. 4 0 0 Scissors are need on Day 5 Lead times - 1 day for
A product structure tree BOM is shown
below.
Scissors are need on Day
Lead times day for each component and
final scissor assembly, and days for the
plastic grips
On hand inventory: Bottom Blade Assembly
Straight Blade and Bent Plastic Grips
Answer the following questions
Determine the planned order release of scissors
how many and when?
Determine the planned order release of the
bottom blade assembly how many and when?
Determine the planned order release of the
straight blade how many and when?
Determine the planned order release of the bent
plastic grips how many and when?