Question: A product structure tree ( BOM or tree diagram ) for the scissors is shown below. 6 0 0 scissors are needed on Day 6

A product structure tree (BOM or tree diagram) for the scissors is shown below.
600 scissors are needed on Day 6(as shown in the master production schedule below).
Lead times are 1 day for each component and final scissor assembly, but 2 days for the plastic grips.
On hand inventory: Straight blades =200, bent blades =350, and top blade assembly =40.
 A product structure tree (BOM or tree diagram) for the scissors