Question: In Class Example A product structure tree ( BOM ) is shown below. 4 0 0 Scissors are need on Day 5 Lead times -
In Class Example
A product structure tree BOM is shown below.
Scissors are need on Day
Lead times day for each component and final scissor assembly, and days for the plastic grips
On hand inventory: Bottom Blade Assembly Straight Blade and Bent Plastic Grips
Answer the following questions
Determine the planned order release of scissors how many and when?
Determine the planned order release of the bottom blade assembly how many and when?
Determine the planned order release of the straight blade how many and when?
Determine the planned order release of the bent plastic grips how many and when?
Bottom Blade Assembly
Top Blade Assembly
Straight Blade
Straight Plastic Grip
Bent Blade
Bent Plastic Grip
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock