Question: A project being analyzed by PERT has 40 activities, 8 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 40 activities, 8 of which are on the critical path. If the estimated time along the critical path is 200 days with a project
standard deviation of 20 days, find the project deadline that gives this project a 32% chance of on-
time completion
.