Question: A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 55

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 1% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.) from 150.95 to 151.07 days O from 151.43 to 151.55 days from 151.07 to 151.19 days from 151.19 to 151.31 days O from 151.31 to 151.43 days