Question: A project being analyzed by PERT has 38 activities. 16 pf which are on the critical path . ifcthe estimated time alontthe critical paath id
A project being analyzed by PERT has 38 activities. 16 pf which are on the critical path . ifcthe estimated time alontthe critical paath id 90 days with a variance of 25 . what is the probability the project will be completed in 88 days or less