Question: A project being analyzed by PERT has 5 0 activities, 1 2 of which are on the critical path. If the estimated time along the

A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the critical path is 176 days with a project variance of 144, the probability that the project will take 194 days or less to complete is
Question 37 options:
near zero.
2.00.
0.9332.
0.0126.
0.0668.