Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is

 A project being analyzed by PERT has 38 activities, 16 ofwhich are on the critical path. The estimated time along the critical

path is 90 days with a project variance of 20 . What
due date will give the project a 0.85 probability of completion? Select

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is 90 days with a project variance of 20 . What due date will give the project a 0.85 probability of completion? Select the range that includes the corresponding completion time in days. Standard Normal Table between 100.5 days and 105.5 days between 95.5 days and 100.5 days more than 105.5 days between 90 days and 95.5 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!