Question: A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find th